20 KLD STP PMJ Somajiguda

PMJ SOMAJIGUDA

20 KLD Sewage Treatment PlantSmart Wastewater Treatment for Sustainable Water Reuse

ROAR Engineers successfully designed and installed a 20 KLD Sewage Treatment Plant (STP) for PMJ Somajiguda, Hyderabad. The project was implemented to reduce the facility’s dependency on fresh water by treating wastewater and reusing it for suitable non-potable applications.

Our Solution for PMJ Somajiguda

PMJ was previously purchasing approximately 20 KL of fresh water every day. ROAR Engineers implemented a 20 KLD STP to treat the wastewater generated at the facility and make the treated water available for reuse.

Reduce Fresh Water Dependency

The 20 KLD STP was designed to treat wastewater generated from the facility, reducing the need to continuously purchase fresh water.

Biological Wastewater Treatment

The STP uses biological treatment to reduce organic pollutants and improve the quality of treated wastewater.

Clarification & Filtration

After biological treatment, the water undergoes clarification and filtration to remove suspended solids and further improve water quality.

Treated Water Reuse

The treated water is reused for suitable non-potable applications, helping PMJ significantly reduce its fresh-water requirement.

From 20 KL to Just 5 KL

20KL

Previous fresh-water requirement per day

15 KL

Treated water reused per day

5 KL

Fresh water now purchased per day

75% Reduction in Fresh-Water Requirement

The project enables approximately 15 KL of water to be reused every day, reducing PMJ’s fresh-water purchase from approximately 20 KL to 5 KL per day.